The MARINA Cagayan de Oro Office Building in El Salvador City, Misamis Oriental has progressed its construction to 54.35%.

The MARINA-CDO, together with the Department of Public Works and Highways Region (DPWH) Region 10 conducts project supervision on the construction site on 15 February 2024.

The first floor’s walls have been finished, while ongoing installation of concrete hollow blocks for walling on the third floor, and the roof deck slab’s concrete pouring and waterproofing are all part of the reported construction development.

The office building is expected to be completed this year.